Financials

Fixed Price - Platform Upgrade

Financial Summary

Forecast to completion details

Time to completion

5 months

Revenue to date

£36,133

Budget remaining

£143,867

Forecast Revenue

£47,600

Budget delta

+£96,267

Forecast Cost

£26,050

Actuals to Date

Staff Days Oct 25 Nov 25 Dec 25 Total
Daniel Fox --2.0 11.0
Frank Lynch 7.0-- 37.1
Eve Thornton -4.0- 22.9
T&S
T&S Spend 000 0
Total Days Billed 7.0 4.0 2.0 71.0
Total Cost £0 £2,200 £1,300 £19,763
Earned Revenue £0 £4,000 £2,400 £36,133
Margin 0.0%45.0%45.8% 45.3%

Forecast

Edit Staff Days Jan 26 Feb 26 Mar 26 Apr 26 May 26 Total
Daniel Fox 2.02.01.01.01.0 13.0
Frank Lynch 8.06.06.06.06.0 54.0
Eve Thornton 5.05.03.03.03.0 32.0
T&S
T&S Spend 00000 0
Total Forecast Days 15.0 13.0 10.0 10.0 10.0 99.0
Forecast Cost £4,050 £4,050 £2,300 £2,300 £2,300 £26,050
Forecast Revenue £7,400 £7,400 £4,200 £4,200 £4,200 £47,600
Forecast Margin 45.3%45.3%45.2%45.2%45.2% 45.3%