Financials

Phase 2 - Implementation

Financial Summary

Forecast to completion details

Time to completion

0 months

Revenue to date

£71,117

Budget remaining

£148,883

Forecast Revenue

£27,150

Budget delta

+£121,733

Forecast Cost

£14,350

Actuals to Date

Staff Days Jan 25 Feb 25 Mar 25 Apr 25 May 25 Jun 25 Jul 25 Aug 25 Sep 25 Oct 25 Nov 25 Dec 25 Total
Grace ONeill -4.0--2.0-3.02.0-1.0-- 12.0
Henry Zhao --4.9-5.0-4.0-5.0-4.0- 22.9
Isla Dunbar ---7.1-8.0-7.09.0-6.0- 37.1
T&S
T&S Spend 000000000000 0
Total Days Billed - 4.0 4.9 7.1 7.0 8.0 7.0 9.0 14.0 1.0 10.0 - 71.9
Total Cost £0 £2,800 £2,677 £3,180 £4,150 £3,600 £4,300 £4,550 £6,800 £700 £4,900 £0 £37,657
Earned Revenue £0 £5,200 £5,110 £6,007 £7,850 £6,800 £8,100 £8,550 £12,900 £1,300 £9,300 £0 £71,117
Margin 0.0%46.2%47.6%47.1%47.1%47.1%46.9%46.8%47.3%46.2%47.3%0.0% 47.0%

Forecast

Edit Staff Days Total
Grace ONeill 3.0
Henry Zhao 10.0
Isla Dunbar 15.0
T&S
T&S Spend 0
Total Forecast Days 28.0
Forecast Cost £14,350
Forecast Revenue £27,150
Forecast Margin 47.1%