Financials

Hybrid - T&M Expansion

Financial Summary

Forecast to completion details

Time to completion

0 months

Revenue to date

£13,550

Budget remaining

£18,450

Forecast Revenue

£8,250

Budget delta

+£10,200

Forecast Cost

£4,400

Actuals to Date

Staff Days Feb 25 Mar 25 Apr 25 May 25 Jun 25 Total
Kim Taylor 3.01.14.08.02.0 18.1
T&S
T&S Spend 00000 0
Total Days Billed 3.0 1.1 4.0 8.0 2.0 18.1
Total Cost £1,200 £427 £1,600 £3,200 £800 £7,227
Earned Revenue £2,250 £800 £3,000 £6,000 £1,500 £13,550
Margin 46.7%46.7%46.7%46.7%46.7% 46.7%

Forecast

Edit Staff Days Total
Kim Taylor 11.0
T&S
T&S Spend 0
Total Forecast Days 11.0
Forecast Cost £4,400
Forecast Revenue £8,250
Forecast Margin 46.7%